BEDFORD HOUSE RELOCATION TIMELINE:

  • October 2005 City of Calgary expropriates Bedford House due to Stampede Park expansion
  • 2006 Sunalta Site Application was approved by the City of Calgary, however SDAB rules against City approval
  • January 2010 CJHS identifies 4444 Builders Road SE as a potential site
  • March 2010 An application was made to the City of Calgary for a Land Use Redesignation
  • July 2010 Land Use Redesignation was approved by City Council
  • August 2011 City of Calgary and the CJHS initiates a Good Neighbour Agreement
  • Fall 2011 CJHS starts designing the facility
  • December 2011 Good Neighbour Agreement is drafted and is almost complete
  • February 2012 Development Permit Preview to the General Public
  • February 2018 Construction Begins
  • June 2019 Construction Completion